A new construction work has 10 work packages designated as A to J. Table 4.22 has pertinent details.

A new construction work has 10 work
packages designated as A to J. Table 4.22 has pertinent details for the
project.

Don't use plagiarized sources. Get Your Custom Essay on
A new construction work has 10 work packages designated as A to J. Table 4.22 has pertinent details.
For as low as $7/Page
Order Essay

(a) Make a network representation of the
project and identify alternative paths in the network

(b) What is the project duration?

(c) The project management team realized a
major omission in one work package. The omitted work package (designated as K)
has ‘C’ as the predecessor and ‘H’ as the successor. The duration of this work
package is 4 months. Will there be a change in the project duration after
inclusion of this work package into the project?

(d) Identify the work packages with
non-zero slack.